DSD HILGERS Stahlbau GmbH

Containercrane with teleskopierbaren Greifzangenspreadern

Place: GVZ Bayernhafen Nürnberg/Germany

Client: TriCon Container-Terminal Nürnberg GmbH

Maximum load bearing capacity on the spreader: 41t

Track gauge: 39.800mm

Hoisting high: 12.500mm

Crane travel speed: 120 m/min

Cross travel speed: 100 m/min

Rotation speed: 1,5-2 U/min

Hoisting speed at full lifting capacity: 15m/min

Hoisting speed in weak field operation: 30m/min

Brammenumschlagkran mit Magnettraverse

Place: Hafen Walsum-Süd

Client: Eisenbahn und Häfen GmbH

Maximum load bearing capacity on the magnet cross beam: 36 t

Track gauge: 33.400 mm

Hoisting High: + 6.500 mm (OK Kaimauer), -15.500 mm (UK Magnettraverse)

Crane travel speed: max. 80 m/min.

Cross travel speed: max. 140 m/min.

Hoisting speed at full lifting capacity: 45 m/min.

Hoisting speed in weak field operation: 90 m/min

Containercranes Nürnberg-Roth

Place: GVZ Hafen Nürnberg Roth

Client: Hafen Nürnberg Roth GmbH

Maximum load bearing capacity on the spreader: 41 t

Track gauge: 39.800 mm

Hoisting height: max. 12.500 mm

Crane travel speed: max. 120 m/min.

Cross travel speed: max. 80 m/min.

Hoisting speed at full lifting capacity: 20 m/min.

Hoisting speed in weak field operation: 40/50 m/min

Containercranes Köln-Eifeltor

Place: Ubf Köln Eifeltor

Client: DB Netz AG

Maximum load bearing capacity on the spreader: 41 t

Track gauge: 39.500 mm

Serviceable length, cantilever arm: 6.750m

Hoisting height: max. 12.000 mm

Crane travel speed: max. 120 m/min.

Cross travel speed: max. 80 m/min.

Rotation speed: 2 U/min.

Hoisting speed at full lifting capacity: 15 m/min.

Hoisting speed in weak field operation: 30 m/min

Power plant Voerde

Place: Voerde, Germany

Client: RWE Power AG

Construction period: 2005

Scope of supply: partial renewal flue gas desulfurization

Suspended railway Wuppertal, superstructure Ohligsmühle

Place: Wupptertal, Germany

Client: Wuppertaler Stadtwerke

Construction period: 2002

Scope of supply: 170t superstructure Ohligsmühle

Power plant Westfalen

Place: Hamm, Germany

Client:
Alstom Power Systems

Construction period: 2010

Construction weight:
6.000t

Scope of supply:
erection of boiler frame

Salzachbridge

Place: Laufen/Germany

Client: Straßenbauamt Traunstein

Construction period: 2002

Scope of supply: Renovation of monument-protected steel structures

Paddle wheel ship “Goethe”

Place: Köln, Germany

Client: Köln-Düsseldorfer Dt. Rheinschiffahrt AG

Scope of supply: modification from steam drive to diesel-hydraulic drive

Power Plant Maritza East 1

Place: Galabovo, Bulgarien

Client: Alstom Power Systems

Construction period: 2008-2010

Construction weight: 11.300t

Scope of supply: erection works

Previous Next